10/21/09 Well this is a long over due update. The lodge is looking beautiful. We are almost completely done with Phase 2 of our project.
2/12/09 The new exterior walls for the bathrooms are done as is the interior wall and plumbing. We are now just waiting on our final inspection so we can start finishing all the drywall in the phase 2 area. Thank you to all of those volunteers that have given their time to help us with this project, the Lord has blessed us with all of their hard work. We'll try to have more photos up soon for you all to see.
11/20/08 We have begun phase 2 of our remodel of the main lodge. This past week we removed the interior walls which will be home of the new lobby and public restrooms.